Unloading machine control system upgrade

Unloading machine control system upgrade

First, the function and structure of the unloading machine

The unloading machine is composed of a bottle conveying device, a conveying device, a bottle grab device, a double four-bar linkage mechanism, a frame, a pneumatic device, an electric control system and the like. When the plastic box filled with the beer bottle passes away from the belt, the cylinder of the tank rises to stop the box, and the cylinder of the box drives the box to separate the boxes, so that each bottle is facing a bottle grabbing device, and the bottle grab device is dropped to On the bottle, grab the cylinder and move the bottle, then grab the bottle, then lift the bottle to place the bottle on the bottle table, let go of the empty box, and then refill the box filled with the bottle. There are 6 unloading boxes at a time, and 24 bottles per box, so 144 bottles are unloaded at a time.

The mechanical part is relatively simple, the wearing parts are replaced every year, and the operation is good; the electric part is mainly driven by two synchronous motors to drive the double four-bar linkage mechanism. In order to ensure the synchronous operation of the two motors, the encoder is installed on the motor, and the PLC can read at any time. The data is compared and automatically adjusted to ensure that the two motors are synchronized; the stop, bin, and each cylinder operate according to the value of the encoder, so the value of the encoder is critical.

Second, the transformation of ideas and processes

The cause of the failure was PLC damage. In order to lay the foundation for other equipment renovation and save money, the company decided to upgrade the unloader and upgrade the control system to the S7-300 control system. The upgrade is divided into two parts: hardware and software upgrade.

Third, the transformation time and effect

1. The specific time of the transformation

On May 20th, the company decided to adopt the upgrade method. From the 21st, we started to contact Siemens to purchase the PLC card of S7-300 series, and started to write the program. On June 1st, we installed the PLC card and started wiring. During the commissioning, some procedures were repeatedly revised and finally delivered to the workshop on June 10th. The transformation time was 20 days.

2, the transformation effect

In terms of the performance of the unloading machine: some operators' suggestions have been adopted. The function of the unloading machine after upgrading and transformation is more practical, more convenient to operate, and reduces the intermediate downtime. In the spare parts management, due to the use of the control system of the S7-300, Siemens S7-300 series of card parts market is very much, after calculation, the original S5 needs 120,000 spare parts, now only 18,000 yuan, is conducive to spare parts management; in terms of saving money: this upgrade and transformation saves money than replacing S5 devices 8 Ten thousand yuan.